Week 1 - Monday 21 August to Friday 25 August

    The following progress was made in week 1:
    - Excavation of trenches along the western elevation for the proposed stormwater network has commenced.
    - Installation of the roof box gutter plywood is underway.
    - Concrete rectification and surface patching of grandstand stairs are on-going.
    - Investigation works of the installed hydraulic and stormwater systems completed.
    - Investigation of the installed electrical systems has commenced.

    Week 2 - Monday 28 August to Friday 1 September

    • The stormwater connection into the OSD tank has commenced.
    • The western stormwater system has been completed.
    • On-going box gutter timber replacement and installation of the waterproof membrane.
    • Installation of drainage channels to top grandstand steps surface.
    • The Allan Border Statue has been completed off-site and design for it's base completed.

    Week 3 - Monday 4 September to Friday 8 September

    Progress completed this week:
     • The box gutter timber replacement and water membrane has been completed.
     • The northern stormwater works are underway.
     • Cleaning of the structural steel structure Frame on level 1 is in progress.
     • Skylight frames have been fabricated off site and to be fabricated shortly.

    Week 4 - Monday 11 September to Friday 15 September

    • The structural steel rectification works have commenced to the perimeter steel beam. 
    • The installation of the roof hip cap along the raked ridge has commenced.
    • Completion of the waterproofing membrane underlayer beneath the box gutter and zinc roof sheets.
    • On-going stormwater works to the northern area with significant rock encountered.
    • Completion of the rectification works to the concrete seats.

    Week 5 - Monday 18 September to Friday 22 September

    • External stormwater works has been completed.
    • Installation of zinc roofing has commenced to the western elevation.
    • Installation of level 1 electrical cabling has commenced.
    • On-going structural steel works to perimeter PFC beam
    • On-going internal concrete rectification works.
    • Placement of drainage gravel and pipe between tiered seating has been completed.


    Week 6 - Monday 2 October to Friday 6 October

    • Commencement of the rainwater treatment plant works.
    • On-going installation of level 1 electrical cable installation.
    • On-going installation of ground floor plumbing works.
    • The zinc roofing has progressed along the northern and southern elevations.
    • On-going installation of structural steel.

    Week 7 - Monday 9 October to Friday 13 October

    • Commencement of the water mains connection. 
    • On-going installation of level 1 electrical cable installation.
    • On-going Installation of level 1 fire service cable installation.
    • On-going installation of level 1 and ground floor plumbing works.
    • The zinc roofing has progressed across all four elevations.
    • On-going installation of structural steel for L1 windows and L1 floor plates.
    • On-going concrete rectification to L1 slanted wall 


    Week 8 - Monday 16 October to Friday 20 October

    • Completion of the water mains connection.
    • Completion of the electrical services rough-in throughout the building.
    • On-going Installation to the fire service cables.
    • On-going installation to plumbing rough-in works,
    • Completion of zinc roofing.
    • On-going installation of structural steel windowsill plates 
    • On-going concrete rectification to L1 slanted wall

    Week 9 - Monday 23 October to Friday 28 October

    • Commencement of GF mechanical penetrations. 
    • On-going installation of plumbing works throughout. 
    • Completion of zinc roof sheet installation
    • Completion of the box gutter installation. 
    • On-going installation of structural steel to western elevation.
    • On-going concrete rectification to L1 slanted wall.

    Week 10 - Monday 30 October - 3 November

    • Commencement to GF mechanical penetrations.
    • Installation of high-level glazing to the oval-side elevation.
    • Commencement of tiling works to rectified patching works.  
    • Commencement to L1 partition walls.
    • On-going installation of plumbing works throughout.
    • On-going installation of structural steel throughout.
    • On-going concrete rectification to the oval side external concrete wall.

    Week 11 - Monday 6 November to Friday 10 November

    • Installation of glazing to high-level oval-side windows.
    • Installation of solar panels has commenced.
    • Installation of the mechanical roof ventilators has been completed.
    • Relocation of the main switchboard to inside the building.
    • Commencement of final trim around external perimeter levels
    • On-going concrete rectification to external concrete wall/s.
    • Placement of steel and formwork for internal concrete slabs.
    • Commencement of tiling patching rectification works.
    • On-going installation of plumbing works throughout.
    • On-going installation of structural steel throughout.
    • On-going adjustments to internal ceiling sliding tracks.

    Week 12 - Monday 13 November to Friday 17 November

    • Completed installation of skylight framing.
    • Completed and poured remaining internal topping slabs.
    • Commenced installation of top-hats for click-on ceiling battens.
    • Commenced installation of acoustic ceiling insulation boards.
    • Commenced structural steel painting works.
    • On-going concrete rectification to external concrete wall/s.
    • On-going installation of level one wall partitions.
    • On-going installation of external stormwater trench grates.
    • On-going installation of structural steel throughout.
    • On-going detailed excavation around building perimeter.

    Week 16 - Monday 11 December to Friday 15 December

    • Completed installation of skylight glazing
    • Completed perimeter building slab concrete.
    • Completed painting of structural steel elements.
    • Commenced installation of timber ceiling batons.
    • Commenced honing of ground floor concrete
    • Commenced installation of retaining wall formwork
    • On-going rectification of external concrete walls
    • On-going installation of mechanical ductwork
    • On-going installation of wall partitions
    • On-going installation of glass window panels.
    • On-going rectification of structural steel.
    • Removal of perimeter roof rails.
    • Removal of scaffold to western and southern elevations.

    Week 21- Monday 8 January to Friday 12 January

    • On-going installation of timber ceiling battens.
    • On-going installation of internal plumbing fixtures.
    • On-going rectification of internal concrete walls
    • On-going installation of mechanical ductwork.
    • On-going installation of wall partitions.
    • On-going installation of glass window panels.
    • On-going installation of internal light fixtures.
    • Completed painting of structural steel members.

    Week 26- Monday 12 February to Friday 16 February

    • On-going construction of external concrete paths, walls, seats and stairs.
    • On-going polishing to level one club room flooring.
    • On-going rectification of internal concrete walls and ceilings.
    • On-going installation of mechanical systems.
    • On-going installation of timber veneer panels to external facade.
    • Commencement of toilet partitions.
    • Completion of tiling to accessible toilets.
    • Completion of timber ceiling battens.
    • Fit-off of security access card readers, cameras.
    • Fit-off of fire EWIS speakers and emergency spitfire lighting.

    Week 31 - Monday 18 March to Friday 22 March

    • Completion of external concrete paths, walls, seats and stairs.
    • Completion of polishing to first floor slab.
    • Completion of the pre-cast grandstand treads.
    • Completion of western angled glass windows.
    • Completion of concrete rectification works throughout.
    • Completion of level 1 sliding doors and glazing.
    • On-going fit-off of electrical, hydraulic and mechanical trades.
    • On-going installation of timber veneer panels to external facade.
    • On-going installation of internal sliding door frames.
    • On-going installation of joinery throughout.
    • On-going installation of metalwork.
    • On-going installation of external light posts, bollards and tree up lights.
    • Commenced installation of external paving.

    Week 35 - Monday 8 April to Friday 12 April

    • Completed sandblasting and sealing works to external concrete areas.
    • Completed installation to toilet and shower partitions.
    • Completed all painting works.
    • Completed installation to timber ceiling battens. 
    • Completed cutting concrete for bottom tracks of sliding doors. 
    • Completed installation of pivot screen doors to the first floor.
    • Completed installation of external timber veneer panels.
    • On-going fit-off of electrical, hydraulic and mechanical trades.
    • On-going installation of ground floor sliding door frames.
    • On-going installation of internal joinery throughout.
    • On-going installation of metalwork to changerooms.
    • On-going installation of external light posts, bollards and tree up lights.
    • On-going installation of tactiles and stair nosing. 

    Week 39 - Monday 6 May to Friday 10 May

    • Completed installation of all ground floor sliding doors.
    • Completed final paint touch-ups to all metal work structures throughout.
    • Completed turfing, mulching and planting throughout the landscape.
    • Completed final fit-off of light fixtures,
    • Completed installation of joinery desks, cupboards and wall panels throughout.
    • Completed installation of handrails, tactiles and stair nosing's.
    • Completed installation of statue onto base.
    • Completed installation of external light posts and bollards.
    • Completed installation of metal sinks and hooks within both changerooms.