Progress
- The structural steel rectification works have commenced to the perimeter steel beam.
- The installation of the roof hip cap along the raked ridge has commenced.
- Completion of the waterproofing membrane underlayer beneath the box gutter and zinc roof sheets.
- On-going stormwater works to the northern area with significant rock encountered.
- Completion of the rectification works to the concrete seats.
- External stormwater works has been completed.
- Installation of zinc roofing has commenced to the western elevation.
- Installation of level 1 electrical cabling has commenced.
- On-going structural steel works to perimeter PFC beam
- On-going internal concrete rectification works.
- Placement of drainage gravel and pipe between tiered seating has been completed.
- Commencement of the rainwater treatment plant works.
- On-going installation of level 1 electrical cable installation.
- On-going installation of ground floor plumbing works.
- The zinc roofing has progressed along the northern and southern elevations.
- On-going installation of structural steel.
- Commencement of the water mains connection.
- On-going installation of level 1 electrical cable installation.
- On-going Installation of level 1 fire service cable installation.
- On-going installation of level 1 and ground floor plumbing works.
- The zinc roofing has progressed across all four elevations.
- On-going installation of structural steel for L1 windows and L1 floor plates.
- On-going concrete rectification to L1 slanted wall
- Completion of the water mains connection.
- Completion of the electrical services rough-in throughout the building.
- On-going Installation to the fire service cables.
- On-going installation to plumbing rough-in works,
- Completion of zinc roofing.
- On-going installation of structural steel windowsill plates
- On-going concrete rectification to L1 slanted wall
- Commencement of GF mechanical penetrations.
- On-going installation of plumbing works throughout.
- Completion of zinc roof sheet installation
- Completion of the box gutter installation.
- On-going installation of structural steel to western elevation.
- On-going concrete rectification to L1 slanted wall.
- Commencement to GF mechanical penetrations.
- Installation of high-level glazing to the oval-side elevation.
- Commencement of tiling works to rectified patching works.
- Commencement to L1 partition walls.
- On-going installation of plumbing works throughout.
- On-going installation of structural steel throughout.
- On-going concrete rectification to the oval side external concrete wall.
- Installation of glazing to high-level oval-side windows.
- Installation of solar panels has commenced.
- Installation of the mechanical roof ventilators has been completed.
- Relocation of the main switchboard to inside the building.
- Commencement of final trim around external perimeter levels
- On-going concrete rectification to external concrete wall/s.
- Placement of steel and formwork for internal concrete slabs.
- Commencement of tiling patching rectification works.
- On-going installation of plumbing works throughout.
- On-going installation of structural steel throughout.
- On-going adjustments to internal ceiling sliding tracks.
- Completed installation of skylight framing.
- Completed and poured remaining internal topping slabs.
- Commenced installation of top-hats for click-on ceiling battens.
- Commenced installation of acoustic ceiling insulation boards.
- Commenced structural steel painting works.
- On-going concrete rectification to external concrete wall/s.
- On-going installation of level one wall partitions.
- On-going installation of external stormwater trench grates.
- On-going installation of structural steel throughout.
- On-going detailed excavation around building perimeter.
- Completed installation of skylight glazing
- Completed perimeter building slab concrete.
- Completed painting of structural steel elements.
- Commenced installation of timber ceiling batons.
- Commenced honing of ground floor concrete
- Commenced installation of retaining wall formwork
- On-going rectification of external concrete walls
- On-going installation of mechanical ductwork
- On-going installation of wall partitions
- On-going installation of glass window panels.
- On-going rectification of structural steel.
- Removal of perimeter roof rails.
- Removal of scaffold to western and southern elevations.
- On-going installation of timber ceiling battens.
- On-going installation of internal plumbing fixtures.
- On-going rectification of internal concrete walls
- On-going installation of mechanical ductwork.
- On-going installation of wall partitions.
- On-going installation of glass window panels.
- On-going installation of internal light fixtures.
- Completed painting of structural steel members.
- On-going construction of external concrete paths, walls, seats and stairs.
- On-going polishing to level one club room flooring.
- On-going rectification of internal concrete walls and ceilings.
- On-going installation of mechanical systems.
- On-going installation of timber veneer panels to external facade.
- Commencement of toilet partitions.
- Completion of tiling to accessible toilets.
- Completion of timber ceiling battens.
- Fit-off of security access card readers, cameras.
- Fit-off of fire EWIS speakers and emergency spitfire lighting.
- Completion of external concrete paths, walls, seats and stairs.
- Completion of polishing to first floor slab.
- Completion of the pre-cast grandstand treads.
- Completion of western angled glass windows.
- Completion of concrete rectification works throughout.
- Completion of level 1 sliding doors and glazing.
- On-going fit-off of electrical, hydraulic and mechanical trades.
- On-going installation of timber veneer panels to external facade.
- On-going installation of internal sliding door frames.
- On-going installation of joinery throughout.
- On-going installation of metalwork.
- On-going installation of external light posts, bollards and tree up lights.
- Commenced installation of external paving.
- Completed sandblasting and sealing works to external concrete areas.
- Completed installation to toilet and shower partitions.
- Completed all painting works.
- Completed installation to timber ceiling battens.
- Completed cutting concrete for bottom tracks of sliding doors.
- Completed installation of pivot screen doors to the first floor.
- Completed installation of external timber veneer panels.
- On-going fit-off of electrical, hydraulic and mechanical trades.
- On-going installation of ground floor sliding door frames.
- On-going installation of internal joinery throughout.
- On-going installation of metalwork to changerooms.
- On-going installation of external light posts, bollards and tree up lights.
- On-going installation of tactiles and stair nosing.
- Completed installation of all ground floor sliding doors.
- Completed final paint touch-ups to all metal work structures throughout.
- Completed turfing, mulching and planting throughout the landscape.
- Completed final fit-off of light fixtures,
- Completed installation of joinery desks, cupboards and wall panels throughout.
- Completed installation of handrails, tactiles and stair nosing's.
- Completed installation of statue onto base.
- Completed installation of external light posts and bollards.
- Completed installation of metal sinks and hooks within both changerooms.
Week 1 - Monday 21 August to Friday 25 August
The following progress was made in week 1:
- Excavation of trenches along the western elevation for the proposed stormwater network has commenced.
- Installation of the roof box gutter plywood is underway.
- Concrete rectification and surface patching of grandstand stairs are on-going.
- Investigation works of the installed hydraulic and stormwater systems completed.
- Investigation of the installed electrical systems has commenced.
Week 2 - Monday 28 August to Friday 1 September
• The stormwater connection into the OSD tank has commenced.
• The western stormwater system has been completed.
• On-going box gutter timber replacement and installation of the waterproof membrane.
• Installation of drainage channels to top grandstand steps surface.
• The Allan Border Statue has been completed off-site and design for it's base completed.
Week 3 - Monday 4 September to Friday 8 September
Progress completed this week:
• The box gutter timber replacement and water membrane has been completed.
• The northern stormwater works are underway.
• Cleaning of the structural steel structure Frame on level 1 is in progress.
• Skylight frames have been fabricated off site and to be fabricated shortly.
Week 4 - Monday 11 September to Friday 15 September
Week 5 - Monday 18 September to Friday 22 September
Week 6 - Monday 2 October to Friday 6 October
Week 7 - Monday 9 October to Friday 13 October
Week 8 - Monday 16 October to Friday 20 October
Week 9 - Monday 23 October to Friday 28 October
Week 10 - Monday 30 October - 3 November
Week 11 - Monday 6 November to Friday 10 November
Week 12 - Monday 13 November to Friday 17 November
Week 16 - Monday 11 December to Friday 15 December
Week 21- Monday 8 January to Friday 12 January
Week 26- Monday 12 February to Friday 16 February
Week 31 - Monday 18 March to Friday 22 March
Week 35 - Monday 8 April to Friday 12 April
Week 39 - Monday 6 May to Friday 10 May